Construction Plan
Click here to go back to the renovation page
Work began: November 1, 2006
Completion of all Essential Aspects: August, 2007
| Phase | Details | Status |
Back Carport |
Remediate back parking lot carport to return 2 parking spots to safe use |
Anticipated 2009/2010 |
Landscaping |
Landscape front and back open areas, including front entryway |
Awaiting funds |
Roof Deck Replacement |
Replace roof deck to similar configuration, improving safety of railing system |
Awaiting funds |
Communal Furniture |
Couches, tables, and chairs for the living room and basement |
Awaiting funds |
Interior Painting |
Paint the complete interior and repair all drywall holes |
Completed! |
Kitchen refresh |
Fix any lingering issues with the kitchen |
Completed! |
Bathrooms Overhaul |
Complete overhaul of all four main bathrooms and toilets. |
Completed! |
Interior room dry wall, trim, and carpet |
Remediate and standardize dry wall, trim, and carpet for all living rooms |
Completed! |
Electrical, Lighting, and Heating Updates |
Update internal wiring and electrical. Improved lighting in sleeping rooms and common areas. New air heating and water heater systems. |
Completed! |
Sleeping Room Remediation |
Replace windows for all sleeping rooms for better insulation and quality of life. Remediate flooring and re-carpet rooms. Standardize closets. Replace and remediate room doors throughout the entire building. |
Completed! |
Roof repairs/ new roof |
Investigate and fix chronic roof leak problems. New roof likely |
Completed! |
Asbestos Abatement |
Remove “hot” tile flooring and drywall. Remove all dust and asbestos threats for further work. |
Completed! |
Demolition |
Remove damaged doors, fixtures, drywall, and bathroom fixtures. Eliminate all waste, old furniture, and broken equipment. |
Completed! |
|